MODULE 3 โ€ข WEEK 9 โ€ข LESSON 35

Scheduling & Timeline Management

Create and manage construction schedules that keep projects on track

โฑ๏ธ 25 min ๐Ÿ“… Schedule builder ๐ŸŽฏ CPM mastery โ“ 8 questions
Module 3
Week 9
Lesson 35
Quiz

The 6-Month, $2 Million Schedule Disaster:

Two builders start identical 20-home subdivisions. Builder A uses a “we’ll figure it out as we go” approach with a basic calendar. Builder B spends 3 days creating a detailed CPM schedule with dependencies, float times, and weather contingencies. Six months later: Builder A has 5 homes complete, crews standing around, and angry buyers threatening lawsuits. Builder B has 15 homes complete, crews flowing smoothly between phases, and buyers moving in early. The difference? Professional schedule management saved 6 months and $2 million in carrying costs, penalties, and lost sales.

1. Critical Path Method: The Foundation of Construction Scheduling

CPM isn’t just a fancy chart – it’s the difference between chaos and profit. Master this, and you’ll deliver every project on time.

๐ŸŽฏ Understanding Critical Path Scheduling

What Makes CPM Different:

โŒ Traditional Calendar Scheduling
  • Lists tasks by date
  • No relationship tracking
  • Can’t see impact of delays
  • No resource optimization
  • Guesswork on completion
โœ… Critical Path Method
  • Shows task dependencies
  • Identifies critical activities
  • Calculates float time
  • Optimizes resource use
  • Predicts completion accurately

The 5 Key CPM Components:

1. Activities

Definition: Specific tasks with defined start/end

Good: “Pour foundation footings”

Bad: “Foundation work”

Break down until you can assign one crew

2. Dependencies

Types of relationships:

  • FS: Finish-to-Start (most common)
  • SS: Start-to-Start
  • FF: Finish-to-Finish
  • SF: Start-to-Finish (rare)

95% of construction uses FS relationships

3. Duration

Calculation: Quantity รท Production Rate

1,000 SF drywall รท 500 SF/day = 2 days

Add weather factor: 2 days ร— 1.1 = 2.2 days

Always round up, never down

4. Critical Path

Definition: Longest path through network

Key fact: Zero float – any delay delays project

RED = Critical GREEN = Float available
5. Float (Slack)

Total Float: Days task can delay without delaying project

Free Float: Days without delaying successors

Use float for:

  • Weather contingency
  • Resource leveling
  • Risk mitigation

2. Building a Professional Construction Schedule

Follow this proven 7-step process to create schedules that actually work in the field:

๐Ÿ“… The Professional Schedule Development Process

1

Work Breakdown Structure (WBS)

Break project into manageable pieces:

Project: Custom Home
โ†’ Phase: Foundation
โ†’โ†’ Activity: Excavation
โ†’โ†’โ†’ Task: Excavate footings

Rule: Stop breaking down when you can assign duration and resources

2

Activity Sequencing

Determine logical relationships:

Construction Logic Questions:
  • What must be complete before this starts?
  • What can happen at the same time?
  • What’s the technical sequence?
  • What are the contract requirements?
  • What are the resource constraints?

Don’t forget lag time:

Pour concrete โ†’ 3 day cure lag โ†’ Frame walls

3

Duration Estimating

Calculate realistic durations:

Duration Formula:

Duration = (Quantity รท Production Rate) ร— Efficiency Factor

Example: (2,000 SF framing รท 400 SF/day) ร— 1.2 = 6 days

Efficiency Factors:
  • Ideal conditions: 1.0
  • Normal conditions: 1.2
  • Difficult conditions: 1.5
  • Winter/rain season: 1.8
4

Resource Loading

Assign crews and equipment:

Resource Rules:
  • No crew in two places at once
  • Maximum crew size limits
  • Equipment availability constraints
  • Subcontractor scheduling conflicts

Resource Leveling: Adjust schedule to smooth out peaks and valleys

Better to have steady 5-person crew than 10 people one day, 0 the next

5

Critical Path Calculation

Forward and Backward Pass:

Forward Pass (Early dates):

ES = Early Start (predecessor EF + lag)

EF = Early Finish (ES + duration)

Backward Pass (Late dates):

LF = Late Finish (successor LS – lag)

LS = Late Start (LF – duration)

Float = LS – ES (or LF – EF)

If Float = 0, activity is CRITICAL

6

Schedule Optimization

Compress schedule without adding cost:

Optimization Techniques:
  • Fast-tracking: Overlap activities (start framing before foundation 100% complete)
  • Re-sequencing: Change logic where possible
  • Resource addition: Add crews to critical path only
  • Shift work: Use non-critical float time

โš ๏ธ Never compress beyond 85% of normal duration

7

Baseline & Communicate

Lock in the approved schedule:

Before Baselining:
  • โœ“ All stakeholders reviewed
  • โœ“ Subcontractors confirmed availability
  • โœ“ Owner approved milestones
  • โœ“ Weather contingency included
  • โœ“ Permits timeline verified

Baseline becomes your measuring stick – track all variances against it

3. Interactive CPM Schedule Builder

Build a real construction schedule using CPM principles:

๐Ÿ“… Construction Schedule Development Tool

Project Information:

days

Add Activities:

4. Schedule Monitoring & Control

Creating the schedule is only 20% of the job – managing it through construction is where the real value lives.

๐Ÿ“Š Professional Schedule Management System

The Weekly Schedule Update Process:

Step 1: Data Collection (Monday AM)

Gather from field:

  • Actual start dates for activities
  • Percent complete for ongoing work
  • Actual finish dates
  • Problems encountered
  • Weather delays

Use daily reports, not memory

Step 2: Schedule Update (Monday PM)

Update sequence:

  1. Enter actuals (starts, finishes, % complete)
  2. Adjust remaining durations
  3. Add new activities if scope changed
  4. Update logic if sequence changed
  5. Recalculate critical path

Never change baseline – track variance instead

Step 3: Variance Analysis (Tuesday AM)

Key metrics to track:

Schedule Variance

Baseline date vs. Projected date

Alert if >5 days

Float Consumption

Original float vs. Remaining float

Alert if <3 days

Critical Path Changes

New activities becoming critical

Alert immediately

Step 4: Recovery Planning (Tuesday PM)

If behind schedule:

Option 1: Crashing

Add resources to critical activities

Cost impact: High

Time saved: Moderate

Option 2: Fast-Tracking

Overlap sequential activities

Cost impact: Low

Risk increase: High

Option 3: Scope Reduction

Defer non-critical work

Cost impact: Savings

Client approval: Required

Step 5: Communication (Wednesday)

Schedule update distribution:

Subcontractors

2-week look-ahead schedule

Their specific dates highlighted

Owner/Client

Milestone status report

Recovery plan if needed

Field Crews

Next week’s detailed plan

Critical path activities marked

Schedule Performance Indicators:

Schedule Performance Index (SPI)

Formula: BCWP รท BCWS

>1.0: Ahead of schedule

<1.0: Behind schedule

Critical Path Variance

Current vs. Baseline completion

Green: 0-5 days late

Yellow: 6-10 days late

Red: >10 days late

Milestone Achievement

% of milestones hit on time

Target: >90%

Minimum: >80%

5. Case Study: The Schedule That Saved a Builder

How proper scheduling turned a disaster into a profit center:

๐Ÿ—๏ธ The Project: Lakeside Custom Homes (12 units)

The Problem:

Contract: 12 homes in 10 months, $500k penalty for late delivery

Month 3 Status:

  • Only 1 home under roof (should be 4)
  • Trades showing up randomly
  • Concrete crew idle 50% of time
  • Framers working overtime on weekends
  • No clear sequence or plan

Projected completion: 16 months (6 months late = $3M in penalties)

The CPM Solution:

Week 1: Emergency Assessment

  • Created detailed WBS for remaining work
  • Identified true critical path
  • Found 15 days of hidden float
  • Discovered foundation crew was bottleneck

Week 2: Schedule Optimization

  • Added second foundation crew ($50k cost)
  • Resequenced to allow 3 homes concurrent
  • Created 2-week look-ahead for all trades
  • Implemented daily progress tracking

Week 3-40: Execution

  • Weekly schedule updates every Monday
  • Daily huddles on critical activities
  • Proactive weather delay management
  • Monthly recovery planning sessions

The Results:

Schedule Performance

Original: 16 months projected

Actual: 9.5 months delivered

2 weeks EARLY!

Financial Impact

Penalties avoided: $3,000,000

Early completion bonus: $250,000

CPM implementation cost: -$75,000

Net benefit: $3,175,000

Efficiency Gains

Crew utilization: 50% โ†’ 85%

Rework reduced: 75% decrease

Overtime costs: 60% reduction

๐Ÿ”‘ Key Lesson:

“The $75k we spent on CPM scheduling returned $3.2 million. That’s a 4,200% ROI. We now CPM schedule everything over $500k.” – Project Manager

โšก Your Schedule Development Challenge

Create Your Construction Schedule (25 minutes):

Develop a CPM schedule for this project:

๐Ÿ  Project: 2-Story Addition (1,200 SF)

Scope: Master suite addition over new garage

Contract duration: 90 days

Key constraints: Owner living in home, rainy season starts day 75

Major phases: Foundation, framing, roofing, MEP rough-in, finishes

Complete Your Schedule:

๐Ÿ“‹ CPM Schedule Template (always visible)

CONSTRUCTION SCHEDULE WORKSHEET

  • PROJECT INFORMATION:
  • Project: 2-Story Addition (1,200 SF)
  • Start Date: _______________
  • Contract Duration: 90 days
  • Target Completion: _______________
  • ACTIVITY LIST WITH DURATIONS:
  • ID | Activity | Duration | Predecessor
  • A | Permits/Mobilization | ___ days | –
  • B | Excavation | ___ days | ___
  • C | Footings | ___ days | ___
  • D | Foundation walls | ___ days | ___
  • E | Backfill/Slab | ___ days | ___
  • F | First floor framing | ___ days | ___
  • G | Second floor framing | ___ days | ___
  • H | Roof framing | ___ days | ___
  • I | Roofing/Dry-in | ___ days | ___
  • J | Windows/Doors | ___ days | ___
  • K | MEP Rough-in | ___ days | ___
  • L | Insulation | ___ days | ___
  • M | Drywall | ___ days | ___
  • N | Interior finishes | ___ days | ___
  • O | Final/Cleanup | ___ days | ___
  • CRITICAL PATH ANALYSIS:
  • Critical path activities: _______________
  • Total duration: ___ days
  • Float available: ___ days
  • KEY MILESTONES:
  • 1. Foundation complete: Day ___
  • 2. Dried-in: Day ___
  • 3. MEP rough inspection: Day ___
  • 4. Final inspection: Day ___
  • RISK MITIGATION:
  • Weather contingency: _______________
  • Critical material orders: _______________
  • Inspection scheduling: _______________
  • SCHEDULE OPTIMIZATION:
  • Fast-track opportunities: _______________
  • Resource conflicts: _______________
  • Proposed solutions: _______________
0 characters

๐ŸŽฏ Schedule Management Mastery

1

CPM shows dependencies and critical path, not just dates

2

Break activities down until you can assign duration and resources

3

Critical path has zero float – any delay impacts completion

4

Weekly updates catch problems while they’re still fixable

5

Fast-tracking and crashing can recover lost time

6

2-week look-ahead keeps subcontractors coordinated

โœ… Schedule Management Mastery Quiz

Question 1:

What does “float” or “slack” represent in CPM scheduling?

Question 2:

Which dependency type is most common in construction (95% of relationships)?

Question 3:

When should you update a construction schedule?

Question 4:

What is “crashing” in schedule management?

Question 5:

Activities on the critical path have how much float?

Question 6:

What does SPI (Schedule Performance Index) > 1.0 indicate?

Question 7:

In the case study, what was the ROI on implementing CPM scheduling?

Question 8:

What efficiency factor should you use for winter/rain season scheduling?

๐ŸŽฏ Ready to Complete Lesson 35?

Take the quiz to finish this lesson and move on to risk management and contingencies.

Students achieving 90%+ across all lessons qualify for potential benefits with lending partners and employers.

โฑ๏ธ Time spent: 25 min ๐Ÿ“š Progress: 34/144 lessons ๐ŸŽฏ Quiz: Not yet taken

Next Up:

Lesson 36: Risk Management & Contingencies – Protect your project from the unexpected