MODULE 4 β€’ WEEK 13 β€’ LESSON 51

Draw Schedules & Fund Management

Master the construction funding process and manage cash flow like a seasoned developer

⏱️ 25 min πŸ“Š Draw tracker πŸ’° Cash flow management ❓ 8 questions
Module 4
Week 13
Lesson 51
Quiz

The $850,000 Cash Flow Crisis:

Two builders start identical $850,000 custom homes in Denver on the same day. Builder A submits his first draw request with incomplete documentation, missing lien waivers, and poor photos. The bank takes 3 weeks to approve $180,000, meanwhile his contractors demand payment. He covers costs with a credit card at 24% interest and falls behind on the next phase. Builder B submits perfectly documented draw requests with detailed progress photos, complete lien waivers, and inspector pre-approval. His draws are approved in 5 days consistently. Builder A finishes 6 weeks late, $47,000 over budget, and nearly bankrupt from carrying costs. Builder B finishes early, under budget, and immediately starts his next project. The difference? Builder B understood that construction draws aren’t just fundingβ€”they’re the heartbeat of successful project management. Today, you become Builder B.

1. Construction Draw Schedule Fundamentals

Construction draw schedules are the structured payment system that releases loan funds as your project progresses. Understanding how they work is critical for maintaining cash flow and project momentum.

πŸ“… How Construction Draws Work

The Construction Draw Process

Step 1: Work Completion

Complete Phase: Finish a major construction milestone

Quality Check: Ensure work meets specifications and quality standards

Documentation: Gather all required paperwork and photos

Timeline: Allow adequate time for proper completion

Step 2: Draw Request Submission

Application: Complete detailed draw request form

Documentation: Submit progress photos, invoices, lien waivers

Inspection Request: Schedule required inspections

Submission Method: Online portal, email, or physical delivery

Step 3: Bank Review and Inspection

Document Review: Bank reviews all submitted documentation

Site Inspection: Bank inspector verifies work completion

Compliance Check: Ensure work meets plans and specifications

Approval Process: Underwriter approves fund disbursement

Step 4: Fund Disbursement

Approval Notification: Bank notifies of approved draw amount

Fund Transfer: Money deposited to designated account

Payment Processing: Pay contractors and suppliers

Record Keeping: Update project financial records

Common Draw Schedule Structures

πŸ—οΈ Phase-Based Draws (Most Common)
Draw 1: Foundation Complete (20%)

Includes: Excavation, foundation, basement walls, waterproofing

Typical Amount: $120,000 on $600,000 project

Requirements: Foundation inspection passed, basement ready for backfill

Draw 2: Framing Complete (35%)

Includes: Full framing, roof structure, sheathing, windows, exterior doors

Typical Amount: $210,000 total ($90,000 additional)

Requirements: Framing inspection passed, structure dried in

Draw 3: Mechanical Rough-In (50%)

Includes: Plumbing, electrical, HVAC rough-in, insulation

Typical Amount: $300,000 total ($90,000 additional)

Requirements: All mechanical inspections passed

Draw 4: Drywall and Interior (70%)

Includes: Drywall, interior trim, flooring, cabinets, countertops

Typical Amount: $420,000 total ($120,000 additional)

Requirements: Interior substantially complete

Draw 5: Final Completion (90%)

Includes: All finishes, fixtures, appliances, landscaping, cleanup

Typical Amount: $540,000 total ($120,000 additional)

Requirements: Certificate of occupancy, final walk-through

Final Draw: Project Close-Out (100%)

Includes: Final punch list items, warranty documentation

Typical Amount: $600,000 total ($60,000 final)

Requirements: Final appraisal, conversion to permanent loan

πŸ“… Monthly Draws

Schedule: Fixed draw dates (e.g., 1st of each month)

Percentage: Based on percentage of work completed

Benefits: Predictable cash flow, easier planning

Challenges: May not align with actual work completion

Best For: Experienced builders with consistent progress

πŸ’° Cost-Plus Draws

Basis: Actual costs incurred with markup

Documentation: Detailed invoices and receipts required

Frequency: Bi-weekly or monthly submissions

Benefits: Covers actual costs, flexible timing

Challenges: More complex documentation, slower processing

Best For: Custom builds with variable costs

Essential Draw Documentation

πŸ“‹ Required Documents for Every Draw
Draw Request Form
  • Completed bank draw request form
  • Requested draw amount with calculations
  • Description of completed work
  • Percentage of project completion
  • Next phase timeline and budget
Progress Documentation
  • Detailed progress photos (before, during, after)
  • Completion certification from contractor
  • Inspection reports and approvals
  • Work completion certificates
  • Quality control checklists
Financial Documentation
  • Invoices for completed work
  • Proof of payment to subcontractors
  • Material receipts and delivery confirmations
  • Updated construction budget vs. actual
  • Change order documentation (if applicable)
Legal Protection Documents
  • Lien waivers from all contractors and suppliers
  • Proof of current insurance coverage
  • Building permit status and inspections
  • Title company updates (if required)
  • Environmental compliance certificates

2. Professional Inspection and Approval Process

Bank inspections are the critical checkpoint for draw approval. Understanding what inspectors look for and how to prepare ensures smooth, fast approvals.

πŸ” Bank Inspection Process

Types of Construction Inspections

πŸ›οΈ Municipal/Code Inspections

Purpose: Ensure compliance with building codes and safety standards

Required For: Permit compliance and legal occupancy

Key Areas:

  • Foundation and structural elements
  • Electrical, plumbing, and HVAC systems
  • Fire safety and egress compliance
  • Accessibility (ADA) requirements
  • Energy efficiency standards

Timeline: Usually required before covering work

Approval Required: Must pass before proceeding to next phase

🏦 Bank Progress Inspections

Purpose: Verify work completion matches draw request

Required For: Fund disbursement approval

Key Areas:

  • Work completion percentage verification
  • Quality of workmanship assessment
  • Compliance with approved plans
  • Budget vs. actual cost analysis
  • Timeline adherence evaluation

Timeline: Within 3-5 business days of draw request

Approval Required: Must approve before fund release

🎯 Third-Party Inspections

Purpose: Independent verification of work quality and progress

Required For: High-value projects or risk mitigation

Key Areas:

  • Structural integrity verification
  • Systems performance testing
  • Quality control assessments
  • Specialized system inspections
  • Environmental compliance checks

Timeline: Scheduled independently by inspector

Approval Required: May be required for certain phases

Preparing for Successful Inspections

πŸ“‹ Pre-Inspection Checklist
Site Preparation
  • Clean and organize work areas
  • Ensure safe access to all inspection areas
  • Remove debris and construction materials
  • Provide adequate lighting for inspection
  • Mark or label key systems and components
Documentation Preparation
  • Have all permits and plans readily available
  • Prepare inspection request forms
  • Organize contractor certifications and warranties
  • Compile change order documentation
  • Prepare progress photos and completion evidence
Work Completion Verification
  • Verify all work matches approved plans
  • Test all systems and components
  • Complete quality control checklists
  • Address any obvious defects or issues
  • Confirm contractor sign-off on completed work
🎯 Inspection Success Strategies
Schedule Strategically

Timing: Schedule inspections early in the week, early in the day

Coordination: Coordinate with contractor to be present

Buffer Time: Allow extra time for potential re-inspections

Weather: Consider weather conditions for exterior inspections

Communicate Proactively

Pre-Call: Call inspector to confirm appointment and discuss any concerns

On-Site: Be present or have knowledgeable representative available

Documentation: Provide clear explanations of any unusual features

Follow-Up: Get written inspection results and next steps

Address Issues Immediately

Minor Issues: Fix small problems on the spot if possible

Documentation: Document any issues and correction plans

Re-Inspection: Schedule re-inspection as soon as corrections are made

Communication: Keep lender informed of any delays or issues

Typical Approval Timeline and Process

Day 1-2: Submission and Initial Review

Borrower Action: Submit complete draw request with all documentation

Bank Action: Initial document review and completeness check

Potential Issues: Missing documents, incomplete forms, unclear photos

Timeline Impact: Incomplete submissions add 3-5 days to process

Day 3-4: Inspection Scheduling and Completion

Bank Action: Schedule and complete site inspection

Inspector Focus: Work completion verification, quality assessment, plan compliance

Potential Issues: Work not ready, access problems, quality concerns

Timeline Impact: Failed inspections add 5-10 days for corrections

Day 5-7: Final Review and Approval

Bank Action: Underwriter review and final approval decision

Review Focus: Budget compliance, project timeline, risk assessment

Potential Issues: Budget overruns, timeline delays, quality concerns

Timeline Impact: Complex issues may require additional documentation

Day 7-10: Fund Disbursement

Bank Action: Process fund transfer to designated account

Borrower Action: Verify fund receipt and process contractor payments

Potential Issues: Banking delays, wire transfer problems

Timeline Impact: Payment processing typically 1-2 business days

3. Professional Draw Schedule Tracker

Track your construction draws, manage cash flow, and ensure timely payments with this comprehensive tracking system:

πŸ“Š Construction Draw Schedule Tracker

⚠️ Professional Use Notice:

This tracker helps manage construction draws and cash flow. Always maintain detailed records and coordinate with your lender’s specific requirements. Proper draw management is critical for project success.

Project Setup

Cash Flow Projection

Draw Request Management

Current Draw Status

Initialize project settings to begin tracking

Next Draw Preparation
πŸ’‘ Professional Draw Management Tips:
  • Documentation: Take detailed photos before, during, and after each phase
  • Timing: Submit draw requests immediately when work is complete
  • Communication: Maintain regular contact with your lender
  • Preparation: Have all documentation ready before starting each phase
  • Contingency: Plan for 10-15 day approval times in your cash flow

4. Strategic Cash Flow Management

Effective cash flow management during construction prevents delays, maintains contractor relationships, and ensures project success. Understanding timing and planning strategies is essential.

πŸ’° Construction Cash Flow Fundamentals

Common Cash Flow Challenges

⏰ Timing Mismatches

The Problem: Contractors need payment before draw funds are available

Common Timing Issues:
  • Labor Payments: Weekly payroll vs. monthly draw schedule
  • Material Deliveries: COD requirements vs. pending draw approval
  • Subcontractor Terms: Net 15 payment terms vs. 10-day draw processing
  • Permit Fees: Upfront costs before any draw availability
  • Inspection Delays: Weather or scheduling delays affecting draw timing
Timing Solutions:
  • Credit Line: Establish construction credit line for timing gaps
  • Payment Terms: Negotiate 30-day payment terms with contractors
  • Draw Acceleration: Submit draw requests before phase completion
  • Supplier Credit: Establish credit accounts with major suppliers
  • Cash Reserves: Maintain 15-20% cash reserves for timing gaps
πŸ“ˆ Cost Overruns

The Problem: Actual costs exceed budgeted amounts, creating funding shortfalls

Common Causes of Overruns:
  • Change Orders: Owner-requested modifications and upgrades
  • Material Price Increases: Market price volatility during construction
  • Unforeseen Conditions: Site conditions not apparent during planning
  • Code Requirements: Updated code requirements during construction
  • Quality Issues: Rework required for substandard workmanship
Cost Overrun Management:
  • Contingency Fund: Build 10-15% contingency into budget
  • Change Order Control: Formal approval process for all changes
  • Regular Monitoring: Weekly budget vs. actual cost analysis
  • Early Warning System: Flag potential overruns before they occur
  • Alternative Financing: Additional funding sources for major overruns
🚧 Construction Delays

The Problem: Project delays create carrying costs and extended financing needs

Financial Impact of Delays:
  • Interest Costs: Extended construction loan interest
  • Carrying Costs: Insurance, permits, utilities during delays
  • Escalation Costs: Material and labor price increases
  • Opportunity Costs: Delayed occupancy or sale
  • Contractor Costs: Potential premium for extended timeline
Delay Mitigation Strategies:
  • Realistic Scheduling: Build buffer time into project timeline
  • Weather Planning: Plan for seasonal weather delays
  • Permit Pre-Planning: Obtain permits before construction starts
  • Material Pre-Ordering: Order long-lead items early
  • Contractor Performance: Select contractors with proven track records

Professional Cash Flow Management Strategies

πŸ“Š Forecasting and Planning
Weekly Cash Flow Forecasting

Purpose: Predict cash needs 4-6 weeks in advance

Sample 6-Week Cash Flow Forecast:
Week 1: Foundation Pour

Cash Needed: $45,000 (concrete, labor, pumping)

Draw Expected: $0 (work in progress)

Net Position: -$45,000 (use reserves)

Week 2: Foundation Completion

Cash Needed: $25,000 (waterproofing, backfill)

Draw Expected: $85,000 (foundation draw approval)

Net Position: +$60,000 (positive cash flow)

Week 3-4: Framing Start

Cash Needed: $75,000 (lumber, framing crew)

Draw Expected: $0 (work in progress)

Net Position: -$15,000 (manageable deficit)

Week 5-6: Framing Completion

Cash Needed: $55,000 (roof, windows, siding)

Draw Expected: $125,000 (framing draw)

Net Position: +$70,000 (strong position)

Phase-Based Budget Planning

Purpose: Align cash needs with draw schedule

Phase Planning Strategy:
  • Pre-Phase Planning: Secure all materials and permits before starting
  • Contractor Coordination: Schedule contractors to minimize idle time
  • Draw Timing: Submit draw requests at optimal completion points
  • Cash Bridge: Plan funding for periods between draws
  • Contingency Access: Maintain access to emergency funding
πŸ’³ Financing and Credit Management
Construction Credit Line

Purpose: Bridge timing gaps between work completion and draw funding

Typical Terms: 6-12 month term, variable rate, 10-20% of project cost

Benefits: Immediate access to funds, pay contractors on time, maintain schedule

Costs: Interest rate typically 2-3% above prime, origination fees

Requirements: Good credit, project documentation, personal guarantee

Supplier Credit Accounts

Purpose: Delay payment for materials until draw funds are available

Typical Terms: Net 30-60 days, 2/10 net 30 discount terms

Benefits: Conserve cash, take advantage of early payment discounts

Requirements: Credit application, trade references, payment history

Management: Track payment dates, take discounts when possible

Personal Asset Management

Purpose: Provide liquidity for unexpected cash needs

Options: HELOC on existing property, investment account margin, business line of credit

Benefits: Quick access, known costs, maintains project momentum

Risks: Personal liability, asset encumbrance, interest costs

Strategy: Use as last resort, minimize exposure time

🀝 Contractor and Supplier Relations
Payment Term Negotiations

Strategy: Negotiate contractor payment terms that align with draw schedule

Effective Negotiation Approaches:
  • Progress Payments: Tie payments to specific milestones vs. calendar dates
  • Retention Terms: Negotiate 10% retention until project completion
  • Draw-Based Payments: Link contractor payments to draw receipt
  • Material vs. Labor: Different payment terms for materials vs. labor
  • Incentive Clauses: Early completion bonuses vs. delay penalties
Communication and Transparency

Strategy: Maintain open communication about cash flow and payment timing

Communication Best Practices:
  • Payment Schedule: Provide contractors with payment schedule upfront
  • Draw Status Updates: Keep contractors informed of draw approval status
  • Issue Resolution: Address payment issues immediately and directly
  • Documentation: Confirm all payment arrangements in writing
  • Relationship Building: Invest in long-term contractor relationships

5. Common Draw Issues and Professional Solutions

Even experienced builders encounter draw issues. Knowing how to identify, prevent, and resolve common problems keeps projects on track and maintains positive lender relationships.

🚨 Common Draw Request Issues

Documentation Issues

Issue: Incomplete or Poor Quality Photos

Problem: Blurry, poorly lit, or incomplete progress photos

Impact on Draw Approval:
  • Delayed approval while requesting better photos
  • Reduced draw amount due to unclear progress
  • Additional inspection requirements
  • Lender confidence issues
Professional Photo Solutions:
  • Quality Standards: Use high-resolution camera or quality smartphone
  • Lighting: Take photos during good lighting conditions
  • Multiple Angles: Capture work from multiple perspectives
  • Before/After: Show clear before and after comparisons
  • Detail Shots: Include close-up photos of critical work areas
  • Progress Sequence: Document work progression over time
Issue: Missing or Incomplete Lien Waivers

Problem: Contractors or suppliers haven’t provided proper lien waivers

Impact on Draw Approval:
  • Complete draw approval hold until waivers received
  • Potential lien risk to lender
  • Project delay while obtaining documents
  • Strained contractor relationships
Lien Waiver Management Solutions:
  • Upfront Education: Educate contractors on lien waiver requirements
  • Template Provision: Provide proper lien waiver templates
  • Payment Coordination: Tie lien waiver receipt to payment
  • Tracking System: Maintain organized tracking of all waivers
  • Regular Follow-Up: Request waivers before work completion
  • Legal Review: Have attorney review waiver language
Issue: Incomplete Financial Documentation

Problem: Missing invoices, receipts, or proof of payment

Documentation Organization Solutions:
  • Digital System: Implement cloud-based document management
  • Real-Time Collection: Collect documents as work progresses
  • Verification Process: Verify document completeness before submission
  • Backup Systems: Maintain multiple copies of critical documents
  • Contractor Requirements: Require contractors to provide documentation promptly

Work Completion Issues

Issue: Work Not Actually Complete

Problem: Draw requested for work that appears incomplete or substandard

Work Completion Solutions:
  • Quality Checklists: Use detailed completion checklists for each phase
  • Independent Verification: Have third party verify completion
  • Contractor Sign-Off: Require contractor certification of completion
  • Pre-Inspection: Conduct own inspection before requesting draw
  • Clear Standards: Define completion standards upfront
Issue: Work Doesn’t Match Plans

Problem: Completed work varies from approved construction plans

Plan Compliance Solutions:
  • Change Order Process: Formal approval for all plan modifications
  • Regular Plan Review: Review plans with contractors regularly
  • Field Verification: Verify plan compliance during construction
  • Documentation: Document and approve all deviations
  • Communication: Maintain clear communication with all trades

Timing and Communication Issues

Issue: Inspector Unavailability

Problem: Bank inspector not available when needed, causing delays

Inspection Scheduling Solutions:
  • Advance Scheduling: Schedule inspections well in advance
  • Flexible Timing: Build flexibility into construction schedule
  • Multiple Options: Provide multiple inspection time options
  • Emergency Contacts: Establish emergency inspection procedures
  • Relationship Building: Develop good relationships with inspectors
Issue: Communication Breakdowns

Problem: Poor communication between borrower, lender, and contractors

Communication Improvement Solutions:
  • Regular Updates: Provide weekly progress updates to lender
  • Single Point of Contact: Designate primary communication contact
  • Documentation: Document all important communications
  • Proactive Communication: Address issues before they become problems
  • Meeting Schedule: Regular scheduled check-ins with all parties

πŸ›‘οΈ Prevention Strategies

Proactive Planning
  • Detailed Scheduling: Create comprehensive project timeline with buffer time
  • Documentation System: Implement organized document management from day one
  • Quality Standards: Establish clear quality and completion standards
  • Communication Protocols: Define communication procedures and expectations
  • Contingency Planning: Plan for common issues and delays
Team Education
  • Contractor Training: Educate contractors on draw requirements and procedures
  • Supplier Coordination: Ensure suppliers understand documentation needs
  • Inspector Relations: Build positive relationships with bank inspectors
  • Lender Communication: Maintain regular communication with construction lender
  • Process Documentation: Document all procedures for team reference

πŸ’° Cash Flow Planning Exercise

Plan Your Construction Cash Flow Strategy (25 minutes):

Apply your knowledge to create a comprehensive cash flow plan for a real construction project:

πŸ—οΈ Project: The Denver Family Home

Project Details:

Location: 3,200 SF custom home in Denver, CO

Total Cost: $720,000 construction budget

Loan Amount: $540,000 (75% LTC)

Your Equity: $180,000 cash down

Timeline: 7-month construction schedule

Start Date: March 1, 2025

Draw Schedule Structure:

Draw 1: Foundation Complete (20%) – $144,000

Draw 2: Framing Complete (35%) – $252,000 total

Draw 3: Mechanical Rough (55%) – $396,000 total

Draw 4: Interior Complete (80%) – $576,000 total

Draw 5: Final Completion (90%) – $648,000 total

Cash Flow Challenges:

Contractor Terms: Most want payment within 15 days

Material Suppliers: 50% require COD, 50% offer Net 30

Draw Processing: Bank takes 7-10 days to approve and fund

Seasonal Factors: Potential winter weather delays

Change Orders: Owner wants $25,000 in upgrades

Create Your Complete Cash Flow Plan:

1. Monthly Cash Flow Forecast (20 points)
  • Project cash needs for each month (March-September)
  • Timing of draw submissions and expected funding
  • Identify potential cash flow gaps
  • Calculate maximum cash exposure
2. Financing Strategy (15 points)
  • Additional financing needed beyond equity
  • Bridge financing for timing gaps
  • Contingency funding for overruns
  • Cost of additional financing
3. Payment Management Strategy (15 points)
  • Contractor payment timing and terms
  • Supplier payment strategies
  • Payment prioritization during cash shortages
  • Relationship management approach
4. Risk Management Plan (10 points)
  • Identify potential cash flow risks
  • Mitigation strategies for each risk
  • Contingency plans for major issues
  • Early warning systems
5. Draw Optimization Strategy (15 points)
  • Documentation preparation checklist
  • Inspection coordination plan
  • Draw submission timing optimization
  • Approval acceleration strategies
6. Implementation Plan (10 points)
  • Tools and systems for cash flow monitoring
  • Communication protocols with team
  • Regular review and adjustment process
  • Success metrics and tracking

Your Cash Flow Management Plan:

πŸ“Š Cash Flow Planning Template (always visible)

DENVER CUSTOM HOME – CASH FLOW MANAGEMENT PLAN

  • PROJECT OVERVIEW:
  • Total Cost: $720,000 | Loan: $540,000 | Equity: $180,000
  • Timeline: 7 months (March – September 2025)
  • Draw Schedule: 5 draws at 20%, 35%, 55%, 80%, 90%
  • MONTHLY CASH FLOW FORECAST:
  • March: Foundation Phase
  • – Cash Needed: $_______ (concrete, excavation, labor)
  • – Draw Expected: $_______ (timing: _______)
  • – Net Position: $_______ (surplus/deficit)
  • April: Framing Phase
  • – Cash Needed: $_______ (lumber, framing, roofing)
  • – Draw Expected: $_______ (timing: _______)
  • – Net Position: $_______ (surplus/deficit)
  • May: Mechanical Rough-In
  • – Cash Needed: $_______
  • – Draw Expected: $_______
  • – Net Position: $_______
  • [Continue for June-September]
  • FINANCING STRATEGY:
  • Maximum Cash Gap: $_______ (month: _______)
  • Additional Financing Needed: $_______
  • Bridge Financing Source: ________________________________
  • Contingency Funds: $_______ (______% of budget)
  • Total Financing Cost: $_______ (interest/fees)
  • PAYMENT MANAGEMENT:
  • Contractor Payment Terms: ________________________________
  • Supplier Payment Strategy: ________________________________
  • Payment Priority System: ________________________________
  • Cash Shortage Protocol: ________________________________
0 characters

🎯 Draw Schedule & Cash Flow Mastery

1

Draw schedules are the heartbeat of construction financing and project success

2

Proper documentation and photos are critical for fast draw approvals

3

Cash flow gaps between work completion and draw funding are inevitable

4

Bridge financing and payment term negotiations manage cash flow risks

5

Lien waivers and compliance documentation prevent draw delays

6

Proactive communication with lenders accelerates approval processes

7

Regular cash flow forecasting prevents financial crises

8

Professional draw management separates successful builders from struggling ones

βœ… Draw Schedules & Fund Management Knowledge Check

Question 1:

What percentage of the project is typically released in the first draw for foundation completion?

Question 2:

What is the typical timeline for bank draw approval and funding?

Question 3:

Which document is most critical for preventing draw delays?

Question 4:

What is the best strategy for managing cash flow gaps between work completion and draw funding?

Question 5:

When should you submit a draw request for maximum efficiency?

Question 6:

What should be included in progress photos for draw requests?

Question 7:

How much cash reserves should you maintain for construction cash flow management?

Question 8:

What is the most common cause of draw request delays?

🎯 Ready to Complete Lesson 51?

Take the quiz to finish this lesson and master construction draw schedules and cash flow management.

Students achieving 90%+ across all lessons qualify for potential benefits with lending partners and employers.

⏱️ Time spent: 25 min πŸ“š Progress: 50/144 lessons 🎯 Quiz: Not yet taken

Next Up:

Lesson 52: Converting to Permanent Financing – Transition from construction to permanent mortgage